1. Executive snapshot
Raisd is building four modern portals (Applicant, Student, Lecturer, Staff) on the existing campus CMS through a single Portal API. The Working Group selected Lesotho as the first acceptance campus (M4) on 3 Oct 2026. Product sequence remains admissions-first: confirm rules (M1) → admissions Live (M2) → core student journeys (M3) → Lesotho acceptance (M4) → other campuses (M5).
2. Progress charts
Same figures as the Overview progress board on the docs site
(portal-api-docs/diagrams/#progress). Charts below are print-safe (no interactive Mermaid).
2.1 Bar — milestone progress %
Frontend started % (sheet) vs estimated platform readiness % (not Live). M1 and M4 have almost no frontend rows.
| Milestone | FE started | Platform | What it means |
|---|---|---|---|
| M1 Confirm rules & integration | 0% | ~45% | Operating / rules milestone. ADR-1, Schema v3 Demo, CAP-53 Partial, architecture docs exist; owners and target weeks still TBC. |
| M2 Admissions launch | 22% (4/18) | ~20% | Student-side starts only. Applicant + staff admissions halves not started. No Live apply→enrol on CMS. |
| M3 Core student portal | 31% (16/51) | ~40% | Deepest student Demo/Partial. Lecturer and staff paths for the same capabilities still 0. |
| M4 Lesotho pilot acceptance | 0% | ~20% | Pilot decided 3 Oct; screenshot inventory + DB gap probe published. Live SoR path and dump still open. |
| M5 Campus expansion | 35% (12/34) | ~25% | Sheet starts + campus inventories (Cyberjaya / Botswana / Sierra Leone). Do not pull ahead of admissions Live. |
2.2 Cumulative readiness over Working Group weeks
Platform work rising; FE started flat at 31% since the 19 Sep sheet; Live stays at 0%. Dates are WG checkpoints, not a committed delivery calendar.
| WG date | Platform | FE started | Live | What changed |
|---|---|---|---|---|
| 18 Sep 2026 | ~15% | 31% | 0% | WG kickoff context; FE snapshot already ~31% from student Demo/Partial. |
| 22 Sep 2026 | ~30% | 31% | 0% | Campus inventories and dump analysis underway. |
| 25 Sep 2026 | ~45% | 31% | 0% | Schema v3 Demo and Portal API / CAP-53 Partial strengthen platform. |
| 1 Oct 2026 | ~55% | 31% | 0% | Docs and campus baselines deepen. |
| 3 Oct 2026 | ~60% | 31% | 0% | Lesotho pilot decided; screenshot inventory and DB gap probe start. |
| 5 Oct 2026 | ~65% | 31% | 0% | Current cut: platform ~65%; FE sheet still flat; Live still 0%. |
2.3 Pie — work mix (applicable frontend rows)
103 applicable M2+M3+M5 frontend rows. Live = 0 omitted. Totals: started 32 · not started 71 · 32÷103 ≈ 31%.
3. Projection, intentions, and goals
3.1 Intended delivery sequence (order only)
Agreed milestone order. Kickoff week and every target week on the sheet remain TBC.
Rules & integration
Admissions Live
Core student
Lesotho accept
Expansion
Distributed CMS
| Order | Milestone | Intention | Release condition (goal) | Target |
|---|---|---|---|---|
| 1 | M1 Confirm rules & integration | Name owners, campus rules, API access, operating responsibilities | Rules and integration access agreed — unblocks later Live work | TBC |
| 2 | M2 Admissions launch | Applicant apply → evidence → offer → enrol on real CMS records; Portal API first slice (CAP-53) | End-to-end admissions Live; staff path via verified old CMS or new screens | TBC |
| 3 | M3 Core student portal | Learning, records, fees, registration with lecturer/staff support paths | Student + staff journeys Live with durable records (Demo alone insufficient) | TBC |
| 4 | M4 Lesotho pilot acceptance | First campus acceptance; parity with Lesotho newer CMS; training & ops | Lesotho campus accepts the integrated pilot | Pilot decided |
| 5 | M5 Campus expansion | Cyberjaya, Eswatini (proposed), Botswana, Sierra Leone, …; progressive CMS consolidation only on verified gaps | Each campus accepts its rollout; no silent SoR rewrites | After M4 |
| Ideal | Distributed Raisd CMS | One product · country/region DBs · white-label · feature flags | Longer-term target after pilot and expansion evidence | Beyond M5 |
3.2 Near-term intentions (next engineering focus)
Protect admissions-first priority
- Freeze non-critical student Demo polish unless it is on the M2 path (auth, accessibility, mobile shell).
- Prioritise CAP-53, applicant CAP-02/03/07/55, and Registry old-CMS verification.
- Keep student demos labelled Demo until wired to durable SoR.
Close leadership blockers (M1)
- Named owners for rules, API access, and operating checks.
- Agree kickoff and first target weeks (currently TBC).
- Confirm backend commitment path for CMS bridge.
Lesotho pilot readiness (M4 path)
- Secure agreed Live SoR path / old CMS dump (no PII in repos).
- Map NMDS, LGCSE, Loti, and newer-CMS parity gaps.
- Treat CAP-41 training/ops as part of acceptance, not an afterthought.
Projected outcome for leadership
- This phase (M1–M4): modern portals on existing CMS; Lesotho accepts first.
- Success metric: Live checklist moves off 0% on admissions, then core journeys.
- Not the goal yet: rewriting every staff desk or pulling M5 ahead of M2 Live.
3.3 Goals by horizon
| Horizon | Goal | Evidence of success | Current state (5 Oct) |
|---|---|---|---|
| Immediate | Leadership lock on M1 owners, access, and target weeks | Named owners + dated plan on the Timeline tab | Open / TBC |
| First Live product | M2 admissions end-to-end on real records | Apply→enrol Live; CAP-53 bridge past stub; staff path verified | Demo started · Live 0% |
| Core campus journeys | M3 student + lecturer/staff paths Live or verified on old CMS | Durable records; paired role actions accepted | Student Demo deepest |
| Pilot acceptance | M4 Lesotho campus acceptance | Campus sign-off; parity with newer CMS for accepted journeys; ops ready | Pilot decided · ~20% |
| Scale | M5 multi-campus rollout + careful CMS consolidation | Per-campus acceptance; migration strategy before retiring desks | Inventories only |
| Ideal end state | Distributed Raisd CMS (country DBs, white-label) | Architecture accepted; no premature rewrite of working SoR | Documented target |
3.4 Definition of done (any capability)
- Real data from the system of record (not a mock session).
- Durable save where the user can mutate data.
- Server-enforced permission for that role and campus.
- Paired staff/lecturer action exists in new UI or is verified in the old CMS.
- Accountable owner named.
- Core mobile accepted if the capability is in the mobile product set.
- Country/campus operating checks closed or explicitly waived.
4. Leadership asks
| # | Ask | Why it matters | Blocks |
|---|---|---|---|
| 1 | Confirm named owners for campus rules, Portal API access, and operating checks | M1 release condition; unblocks “Needs checking” backend rows | M2–M4 planning |
| 2 | Set kickoff and first milestone target weeks (even provisional) | Sheet targets are all TBC; sponsors need a calendar signal | Weekly % credibility |
| 3 | Commit CMS bridge / Live SoR path for Lesotho (and dump access without PII in repos) | Without this, Live stays at 0% regardless of UI polish | M2 Live and M4 acceptance |
| 4 | Reaffirm admissions-first priority over further student Demo expansion | Current build gravity is M3 student UI | M2 critical path focus |
| 5 | Confirm who receives weekly progress PDFs and Demo credentials | Governance cadence for senior review | Reporting rhythm |
5. Sources and reading notes
| Source | Use in this pack |
|---|---|
| SDD-13 Progress timeline (sheet 19 Sep 2026) | FE started / applicable / Live counts |
| SDD-03 Delivery milestones (updated 3 Oct 2026) | M1–M5 sequence, Lesotho M4, definition of done |
| Overview progress board (docs site, 5 Oct 2026) | Charts, platform readiness estimates, WG-week series |
| Working Group 3 Oct 2026 | Lesotho selected as pilot acceptance campus |
| ADR-1 (Aslam, 23 Sep 2026) | Existing CMS family remains SoR this phase |
| Weekly pack 2026-10-03 | Baseline delivery detail for engineering estate |
Companion weekly engineering pack:
docs/reports/weekly-progress-2026-10-03/.
Live board:
https://raisd-campus.github.io/portal-api-docs/diagrams/#progress.